As the days shortened we were keen to get the roof sheetd and shingled so we would finally be able to keep the inside of the house dry. This resulted in a few evenings spent roofing in the dark. This actually turned out to be something of a bonus, as it was a lot less scary standing on the edge of the roof when you couldn't see the huge drop to the ground beneath you.
Roofing was a job that we were able to do on our own (albeit very slowly), but Stan and Nicole continued their helpful visits and we spent our time alternating between roofing and installing windows and doors. The windows and doors were finished first, as we only had the scissor lift for a limited time, and installation was a 4 man job (although somehow Lea always managed to get the easy part!). We eventually got the last window in late one night (and again, just in time, as the generator ran out of gas just as the last screw was tightened). Finally getting the windows and doors in meant that we were able to send back our storage container, which had been the very first thing delivered to our site way back in May. However, the window and door installation was not enbtirely without problem, as we found that our patio doors were defective. We have since had someone out to fix them (which was a bit of a shoddy job), and we have now found another fault with them. Lea plans to thrash the issue out with the manufacturer tomorrow.
It seems like such a long time ago that we started the roofing, that I can barely remember it. I do know that we had days of glorious sunshine, and at times were up there in shirtsleeves. This was all very different to the final few days of shingling, when I had to sweep frost off the roof every morning, and finish the shingling in the snow. The reason the roofing took us so long was that we had to first put down a waterproof membrane, and then nail the shingles down over the top. In addition to this we also had to tar every shingle before it went into place. This was a result of the low pitch of the roof combined with the high wind which seems to be fairly constant here in the prairies.
We weren't helped by the weather during the roofing either. Over the course of two weekends we lost a day to rain, and then a whole weekend to high wind. This was made much worse by the fact that during the weeks, when we were at work, we had great shingling weather but couldn't get any shingling done. The weekend of high wind also caused us a few problems as our scaffolding was blown over, and landed on our generator. Luckily no-one was around at the time so there were no injuries, and looking back, the damage could have been much worse. However, it was still a hugley frustrating episode, but hopfully we can put it behind us and get through the rest of the project incident free.
These photos appear to be in something of a random order, but the views of the roof were taken on the day before we finished with the windows and doors. They illustrate quite nicely how little we had actually achieved on the roof at that point.
We must send our apologies to Carter and Cassidy for ruining so many of their weekends over the summer. While Stan and Nicole helped us out with all our work Carter and Cassidy were left to amuse themselves in and around the house. Hopefully they haven't been too bored.
It was approximately 5 weeks after we started the roof the it was finally finished, and by this time we had had several contractors in to get some stuff done inside the hosue. The electrician arrived and connected the house to the grid so we now have power. It was a huge relief to be able to work without the sound of the generator running constantly in the background. It is quite annoying to think that all over the summer we were burning gas to provide power when gas was close to $1.50 a litre, and now that we don't need to burn gas the price is down below $1 a litre!
Also we have had some of the ductwork installed for the heating and ventilation system, and we had some poeple out to excavate and pour a footing for the garage. This all happened pretty quick and meant that we were able to build the pony wall for the garage (out of polystyrene blocks, and pour the concrete on Monday this week. This was all going very well, until on of the polystyrene blocks broke and we had loads of concrete pouring out from the bottom of the wall. Luckily Lea threw herself at the hole and we managed to get it patched before the whole situation was lost. The worst news was that our geothermal pipes have been ruptured during the excavation of the footing (twice we were aware of the breaks, but there still appears to be a hole somewhere which we can't find). This is very frustrating and is leaving our geothermal contractor with a few headaches at the moment.
We have also received all the insulation for the house. This is a little bit early as we haven't yet put the building paper on, so we have about 50 pallets of insulation waiting outside for us. Hopefully we will get round to insulating pretty soon, although before we can do that we have to frame the garage and paper the entire house. I'm planning on getting the papering done this week, as I am once again off work, this time for 3 months (I should be back at work on Feb 1st, but have been told that I may not be needed until March 1st!!!!!!). I have a lift being delivered tomorow from Hertz so intend to get most of the papering done by the weekend.
We should have our driveway built next week too. This will be pretty useful as our current driveway is very low, and once the snow starts to fall a bit more heavily, will probably be impassable for our small car.
In non house related news this time: the company Lea works for has been bought out by a large engineering firm and has moved into a larger office; the football season has started for me; we attended out very first halloween party in Canada (never dress up in a cow costume when there are kids around!); we will be moving out of our flat at the end of November (however, we are not moving into our own house, we are moving into the basement at Stan and Nicole's); and finally, Hannah has set the date for her wedding (the end of August), so we are likely to be back in England for a couple of weeks in late August/early September.
Please vote in the fish naming poll tune in next time to see what the winning names are.
Until next time,
Rob and Lea
And how could I forget, I started my trapping program in the basement in an attempt to deal with the mouse problem which we seem to be having. I was very impressed with the catching efficiency of our traps when I found 2 mice in the first trap I checked. Sadly I haven't had any more multiple catches since then, but I still hoping for a triple!
